Library boards back American Alarm, Pro-AV bids
Library boards recommended security and AV contracts for Westford's new library. The joint J.V.
Library boards recommended security and AV contracts for Westford's new library. The joint J.V.
Westford library building panel approves $27,900 fence to settle years-long dispute with Main Street neighbor.
The Westford Library Board of Trustees and Permanent Town Building Committee approved a $48,308 change order for emergency chimney repointing at the J.V.
Westford's J.V. Fletcher Library renovation committee approved $1.6 million in June payments and fielded pointed questions about change order transparency at its July 13 joint meeting.
Westford building panel approves $230,000 in library change orders, tables tile dispute.
Westford library joint committee approves $1.53 million warrant and calls emergency meeting for deferred change orders.
Westford library rebuild passes one year, boards approve $1.5 million in payments. The Permanent Town Building Committee and the J.V.
Westford's library trustees and building committee learned the Fletcher Library renovation remains on budget but won't finish within its original 18-month window.